
Receiving the keys to a newly completed home is an important milestone, but before moving in, there is another document homebuyers should know about: the Certificate of Completion and Compliance (CCC).
The CCC confirms that a building has been completed and complies with the relevant requirements for it to be considered safe and fit for occupation. For homebuyers, understanding CCC certification Malaysia requirements can help you know what to check when a developer delivers vacant possession (VP), including whether the appropriate CCC has been issued.
In this guide, we explain what the CCC is, why it matters, who can issue it, how the certification process works, the difference between Form F and Form F1, and how the CCC differs from the older Certificate of Fitness for Occupation (CFO).
Browse apartments, condominiums, and serviced residences for sale in Malaysia.What Is CCC Certification In Malaysia?
The CCC certifies that a building has been completed according to approved plans and applicable statutory requirements, and is safe and fit for occupation. The required building works, certifications, clearances, and essential services must be in place before the CCC can be issued.
Malaysia introduced the CCC system in 2007 to replace the previous CFO system for applicable developments. The Principal Submitting Person (PSP) issues the CCC after the necessary requirements are met, while local authorities retain regulatory powers, including approving plans, carrying out inspections where necessary, and taking enforcement action for non-compliance.
What Is The Difference Between CCC And CFO In Malaysia?
A property in Malaysia may be physically complete, but it must still meet the relevant requirements before it is certified for occupation.
The CCC process provides documented certification of the construction works by the relevant professionals and parties involved in the project.
Among other matters, the certification process can cover works involving:
- Earthworks
- Setting Out
- Foundations
- Structural
- Internal Water Plumbing
- Internal Sanitary Plumbing
- Internal Electrical
- Fire-Fighting (Passive)
- Fire-Fighting (Active)
- Mechanical Ventilation
- Lift/Escalator Installation
- Building
- External Water Supply System
- Sewerage Reticulation
- Sewerage Treatment Plant
- External Electrical Supply System
- Road and Drainage
- Street Lighting
- Street Lighting External Main Drain
- Telecommunication
- Landscape
Before the CCC is issued, the PSP must ensure that the necessary stage certifications and clearances have been obtained.
This gives homebuyers an important distinction to remember: a building appearing finished and a building being properly certified for occupation are not necessarily the same thing.
What Is The Difference Between CCC And CFO In Malaysia?
The CFO was the certification system used before the CCC system was introduced.
The key difference concerns who issues the certification.

The CCC system came into force on 12 April 2007. The change was intended to address delays associated with the previous CFO process by shifting responsibility for certification to qualified professionals involved in the project.
This is also why owners of older properties may encounter a CFO rather than a CCC. The existence of a CFO on an older building does not automatically mean that the property lacks the appropriate completion documentation simply because it does not have a CCC.
Who Can Issue A CCC In Malaysia?
The professional responsible for issuing the CCC is known as the Principal Submitting Person (PSP).
The PSP may be an architect, professional engineer, or registered plan painter, depending on the type of building and applicable professional requirements.
The PSP has a central role throughout the project rather than simply appearing at the end to sign the CCC.
Among the PSP’s responsibilities are:
- Submitting the relevant building plans for approval.
- Supervising the erection and completion of the building.
- Ensuring construction conforms to the approved plans.
- Ensuring the relevant statutory and technical requirements have been complied with.
- Ensuring the necessary stage certifications are completed.
- Checking that required clearances and essential services are in place.
- Ensuring that the completed building is safe and fit for occupation.
- Issuing the CCC when the applicable requirements have been satisfied.
The professional certification system therefore places considerable responsibility on the PSP and the other professionals responsible for individual stages of construction.
How Does The CCC Process Work?

The CCC certification Malaysia process does not begin only when construction is finished. Compliance is documented progressively as construction moves through different stages.
Step 1: Building Plans Are Approved
Before construction proceeds, the relevant plans must go through the required approval process with the local authority and other relevant agencies.
Step 2: Construction Is Carried Out According To Approved Plans
The PSP supervises the project to ensure that the building works comply with the approved plans and applicable requirements.
Step 3: Relevant Parties Certify Individual Stages
Different elements of the construction are certified through a series of prescribed Forms G.
These certifications provide a record that the respective stages of work have been completed in accordance with the applicable requirements.
Step 4: Required Clearances And Services Are Confirmed
The PSP must ensure that applicable technical clearances and required services are in place before issuing the final CCC.
Step 5: The PSP Issues Form F
Once the applicable conditions have been fulfilled, the PSP can issue Form F, which is the CCC.
Step 6: Copies Are Deposited With The Relevant Authorities
The CCC and supporting documentation must be deposited with the relevant local authority and professional board in accordance with the prescribed requirements.
KPKT’s OSC 3Plus guidance states that the PSP should submit Form F to the local authority within 14 days from the date shown on Form F. The PSP must also ensure that Forms G1-G21 have the relevant confirmations, certificates, or clearance documentation required for the issuance of the CCC.
Learn about mortgages and loans with home financing guides.What Are The Key Documents For CCC Certification In Malaysia?
Several documents are involved in property completion and handover. The issuance of a CCC must be supported by 21 Forms G. Eight of the 21 Forms G require a confirmation letter or certificate of qualification from the relevant technical agency.

For Form G17, if the confirmation letter is not received within 14 days from the date of application, the confirmation is deemed to have been granted.
What Are Forms G1-G21 In The CCC Process?
Forms G1-G21 are 21 stage certification forms that document the completion and compliance of different components of building work. They cover key stages such as earthworks, foundations, structural works, plumbing, electrical installations, fire-fighting systems, sewerage, roads and drainage, telecommunications, and landscaping.
The relevant contractors and professionals certify the works under their responsibility as construction progresses. Before issuing the CCC and Compliance, the PSP must ensure that all required Forms G1-G21 are properly completed, together with the necessary confirmations or certificates from the relevant technical agencies.
What Is Form F In CCC Certification?
Form F is the CCC issued by the PSP once the applicable completion and compliance requirements have been fulfilled. Its issuance must be supported by the required Forms G1-G21 and relevant technical clearances.
For housing developments governed by the Housing Development (Control and Licensing) Act 1966 (Act 118), Form F is the CCC required for the delivery of vacant possession. It should not be confused with Form F1, which is a Partial CCC and serves a different purpose.
What Is Form F1 And How Is It Different From Form F?
Form F1 is a Partial Certificate of Completion and Compliance (Partial CCC). It may be issued when a specific portion of a development has been completed and meets the applicable requirements, even though the entire development has not yet been completed. Form F, in contrast, is the full CCC.
The distinction is particularly important for housing developments governed by the Housing Development (Control and Licensing) Act 1966 (Act 118). According to the Department of Local Government (JKT), only Form F is accepted as the CCC required for the delivery of vacant possession (VP), while Form F1 does not satisfy this requirement.
| Form | What It Represents | Vacant Possession Under Act 118 |
| Form F | Full Certificate of Completion and Compliance | Accepted for VP |
| Form F1 | Partial Certificate of Completion and Compliance | Not accepted for VP |
This distinction is particularly important for buyers purchasing homes in larger or phased developments.
Can A Developer Deliver Vacant Possession Without A CCC?
Only the full CCC under Form F is accepted for the delivery of vacant possession (VP). A Partial CCC under Form F1 does not satisfy this requirement, even if a particular portion of the development has already been completed.
Homebuyers should therefore confirm that the developer has provided the relevant Form F CCC when receiving the Notice of Vacant Possession. Receiving the keys or seeing that the property appears physically complete is not a substitute for the required certification, so the handover documents should be checked carefully before taking possession.
Discover new homes for sale in Malaysia and find one that fits your needs.Can A CCC Be Withdrawn After It Has Been Issued?
According to the Department of Local Government (JKT), a CCC cannot be revoked once it has been issued, and the local authority must accept it as legally valid. However, action can still be taken if false certification or non-compliance in the issuance of the CCC is discovered.
The local authority may take action against the PSP under Act 133. It may also refer the case to the Board of Architects Malaysia or Board of Engineers Malaysia for action under the relevant professional legislation, or to the National Housing Department for action against the developer under the Housing Development Act.
Does A CCC Mean A Property Has No Defects?
A CCC confirms that a building has met the applicable completion and compliance requirements for occupation. It does not guarantee that an individual unit is completely free from defects or workmanship issues.
Buyers may still find cracked tiles, leaking fixtures, uneven finishes, faulty fittings, or other defects after receiving vacant possession. A thorough defect inspection is therefore important even when the development has obtained its CCC, so any issues can be identified and reported within the applicable defect liability period.
What Should Homebuyers Check When Receiving A CCC?
Homebuyers do not need to become building professionals to make basic checks when taking possession of a newly completed property.
Start by confirming that the document provided is Form F, CCC, which is the certificate required for your development.
You can also check:
- The property or development details stated on the certificate.
- The date the CCC was issued.
- The details of the PSP signing the certificate.
- Whether you have received Form F rather than Form F1 where a full CCC is required.
- Whether the CCC corresponds with the property for which vacant possession is being delivered.
- Whether the documents supplied match the details in your Sale and Purchase Agreement (SPA) and VP notice.
A CCC does not guarantee a defect-free property. Buyers should still inspect their unit carefully and report any defects within the applicable defect liability period.
Understanding CCC Before Moving In
The CCC is an important part of the property completion and handover process in Malaysia. Form F confirms that the applicable completion and compliance requirements have been fulfilled, while Form F1 is only a Partial CCC.
When receiving vacant possession, check that the appropriate Form F has been issued. Also review your Sale and Purchase Agreement (SPA), VP notice, utilities, access arrangements, and property condition, and complete a defect inspection after receiving your new home.
Ready to explore your options? Browse properties for sale in Malaysia and find a home that suits your needs.
Planning your home loan? Use the Mortgage Calculator to estimate your monthly repayments and budget with confidence.
